THIRUVANANTHAPURAM:
Replacement of 140 Track Kilometres (TKM’s) of rails has to be completed in Trivandrum division in the year 2017-18. The division has two critical single line sections between Kollam-Ernakulam with more than 100 percent line saturation. During the sabarimala season additional 123 additional special train services are operated through this route increasing the traffic density by double. More number of Sabarimala specials are planned near makaravilakku period. The present practice of regulating trains en-route is not sufficient to execute the track maintenance works within the time frame and above all this is causing major inconvenience to passengers due to loss of punctuality which is not predictable.
The four pairs of Passenger/MEMU trains are cancelled on a temporary basis, based on their comparative lower patronage being not covering office commuter timings, for two months based on the following grounds by the Southern Railway Head Quarters, Chennai:
a) To provide a Maintenance Corridor (MC) Line Block between two express trains enabling replacacement of defective rails, sleepers etc and also to finish other critical maintenance works. During the MC Line Block all maintenance departments like Traction Distribution, Signalling etc will co-oridinate and finish their respective maintenance works. Track machines will be additionally utilized to complete the maintenance target.
b)Management of train crew, comprising of Loco pilots and Guard, while introducing seasonal special trains, track machines, ballast trains and freight trains in addition to the regular/weekly Mail/Express/Super fast trains etc are carefully done. Detaining the trains enroute due to maintenance works is observed to affect the mandatory rest hours of crew.
However, a review will be done periodically on the output achieved by the cancellation of the trains, on the basis of maintenance works executed during the MC line block. The possibility of providing alternate train services to passengers in lieu of cancelled passenger trains will also be explored. The scope providing additional stoppages for regular trains is also ascertained to offset the effect of cancellation. The train service may also be restored earlier based on the review.

more recommended stories
Keep Your Response Sharp and Ready to Navigate in Testy Global Scenario: Speakers at TMA’s Management MeetTHIRUVANANTHAPURAM:The relevance of strategic leadership in.
Leverage Tech to Enliven Values in Life: Pooyam Thirunal Gowri Parvathi BayiTHIRUVANANTHAPURAM:It is high time we used.
UK Air Traffic Glitch Triggers Mass Disruptions, Over 100 Flights CancelledLONDON:More than 100 flights were cancelled.
Technopark Honours Legacy of Longtime Technical Member and Guide of 35 YearsTHIRUVANANTHAPURAM:Technopark honoured former Chief Engineer of.
Air India Express Announces ‘Payday Sale’KOCHI:Air India Express has launched its.
Vietjet Makes International Travel More Rewarding This MonsoonMUMBAI:This monsoon, Vietjet is making international.
Vietjet Launches big 7/7 Promotion: Enjoy Flying with up to 77% off all FlightsMUMBAI:This summer, Vietjet is turning up.
Smart Sewage Plant Commissioned at TechnoparkTHIRUVANANTHAPURAM:Technopark commissioned a new Sewage Treatment.
IT Fraternity’s Arts and Lit Fest Awards Given AwayTHIRUVANANTHAPURAM:The 11th edition of ‘Srishti,’ the.
Air India Flights to be Hit From June 21 to July 15 Due to Boeing ChecksNEW DELHI:Air India on Thursday gave.